Reply To: Project plan Dependency Settings

Inner Circle › Ask Smartsheet Guru Crew Anything › Project plan Dependency Settings › Reply To: Project plan Dependency Settings

#704
Michael Drayton
Participant

    So What I’ve done is removed the Predecessors as they are initially setup. I’ve added all the dates and then repopulated the predecessors.

    However, when I add the predecessors its not updating manipulating the dates. Should I use another ID other than WBS?