When dependencies are enabled, you can’t edit the Start Date without breaking the dependency. Think of it this way…
The start data of successor tasks is dependent on the predecessor(s) end dates, so if you want to change the start date of a specific task, you either need to adjust the end date of the predecessor task, or make the task not dependent on another task.
Make sense?