Reply To: UAT-Multiple Users per round

Inner Circle › Ask Smartsheet Guru Crew Anything › UAT-Multiple Users per round › Reply To: UAT-Multiple Users per round

#643
Darren
Keymaster

    Tamarin,
    Ahh, welcome to the fickle client process 🙂 . And don’t worry, you’re not alone in these types of struggles. It’s a common scenario that happens where a client is changing their process on you 😉

    There are different ways to handle this, will take some thinking over before giving a proper response.

    As far as the relation to Q2 and Q1, the answer would be yes if the solution for Q1 is designed in a way that makes this easy.

    Some clarifying quetions.
    1. Is the current task list a project plan with start/end dates and duration, or is it setup as a list of tasks with user assignment and result
    2. Would it make sense to add multiple rows in a parent/child hierarchy? This would be more manual, so that may not be what the client desires.
    3. Do you need to aggregate the results from all users performing a specific test?

    If no to #2, then we’d have to consider other ways to take a specific task, then create another row to allow assignment.